11/17/2001
Construction of my second craft (of the year) has officially begun. I have cleaned out the garage and mounted the plans for the UH-12T4.
The engine pictured is the thrust engine. It is a 440 Yamaha with electric start. :) The lift engine is a B&S 6.5 hp.
After 2 days I have rib R2 completed and ribs 3, 4, 5 & 6 started.





11/25/2001
All of the ribs are finished except for the front rib R1. The plans call for 14 foot 1x4 for the stringers. The longest 1x4 available locally was 12 foot. I ended up getting 14 foot 2x4's and ripping them to the correct dimension. With the stringers cut and the ribs ready, I had to start putting them together. The last pictures show the ribs with the first coarse of stringers.